BASE EARTHMAN - rammed earth oven - first fire (according to calendar)

15 Mar 2020

BASE EARTHMAN - rammed earth oven - removal of wooden formwork

14 Mar 2020

BASE EARTHMAN - rammed earth oven - final result -> freshly born

13 Mar 2020

BASE EARTHMAN - rammed earth oven - wooden formwork before removal

12 Mar 2020

BASE EARTHMAN - rammed earth oven - removal of first formwork layer

10 Mar 2020

BASE EARTHMAN - rammed earth oven - ramming process

8 Mar 2020

BASE EARTHMAN - rammed earth oven - wooden formwork within steel frame

6 Mar 2020

BASE EARTHMAN - 1:1 scale model of rammed earth oven

5 Mar 2020

BASE EARTHMAN - model composition for rammed earth oven

3 Mar 2020

BASE EARHTMAN - kitchen by markus faisst , lamps by basic.work

19 Dec 2019

BASE EARTHMAN - clay lamps meet rammed earth and clay plaster...lamps made by basic.work

16 Dec 2019

BASE EARTHMAN - almost there with first appartment

12 Dec 2019

BASE EARTHMAN - clay plaster finishing

11 Dec 2019

BASE EARTHMAN - last touch up in the kitchen

10 Dec 2019

BASE EARTHMAN - last plumbing in ensuite bathroom

9 Dec 2019

BASE EARTHMAN - interior doors made by our local carpenter arriving...

8 Dec 2019

BASE EARTHMAN - good bye PUTZI!

6 Dec 2019

BASE EARTHMAN - lime plaster

4 Dec 2019

BASE EARTHMAN - wall preparation for lime plaster

3 Dec 2019

BASE EARTHMAN - bathroom - preparation for limeplaster

2 Dec 2019

BASE EARTHMAN - last claywork ... before winter

1 Dec 2019

BASE EARTHMAN - final steps for interior space

30 Nov 2019

BASE EARTHMAN - wooden ceiling

29 Nov 2019

BASE EARTHMAN - kitchen are arriving !!!

28 Nov 2019

BASE EARTHMAN - substrucutre for wooden ceiling

28 Nov 2019

BASE EARTHMAN - recycle concrete bricks from the old parking

26 Nov 2019

BASE EARTHMAN - internal woodwork

25 Nov 2019

BASE EARTHMAN - formwork for rammed earth wall

22 Nov 2019

BASE EARTHMAN - rammed earth in clay plaster

21 Nov 2019

BASE EARTHMAN - rammed earth steps

20 Nov 2019

BASE EARTHMAN - team !! the most mportant

19 Nov 2019

BASE EARTHMAN - sunwashed clay

18 Nov 2019

BASE EARTHMAN - electric installation

17 Nov 2019

BASE EARTHMAN - transformation

16 Nov 2019

BASE EARTHMAN - interior coating

15 Nov 2019

BASE EARTHMAN - clay on concrete blocks

14 Nov 2019

BASE EARTHMAN - wooden ceiling

13 Nov 2019

BASE EARTHMAN clayplaster -> base clay

2 Jul 2019

BASE EARTHMAN a new house is born!!

30 Jun 2019

BASE EARTHMAN north facade --> almost done!!!

28 Jun 2019
almost done!!! -->

BASE EARTHMAN facade finnishing

27 Jun 2019

BASE EARTHMAN facade in process

25 Jun 2019

BASE EARTHMAN extended window frame

25 Jun 2019

BASE EARTHMAN facade structure

25 Jun 2019

BASE EARTHMAN electrical installation

5 Jun 2019

BASE EARTHMAN structural improvement --> avalanche protection

5 Jun 2019
avalanche protection -->

BASE EARTHMAN fixing vapor paper

5 Jun 2019

BASE EARTHMAN roof cladding

5 Jun 2019

BASE EARTHMAN preparation of the separation wall mixture

28 Apr 2019

BASE EARTHMAN cladding repositioning after vapor barrier removal

28 Apr 2019

BASE EARTHMAN roof cladding delivery

28 Apr 2019

BASE EARTHMAN rough roof after tiles removal

28 Apr 2019

BASE EARTHMAN old and new roofs action

28 Apr 2019

BASE EARTHMAN wood profiles delivery

28 Apr 2019

BASE EARTHMAN vapor barrier removal

28 Apr 2019

BASE EARTHMAN clearing off the snow to the prepare the roof deconstruction

28 Apr 2019

BASE EARTHMAN ceiling beams attachment

28 Apr 2019

BASE EARTHMAN working on ceiling beams

28 Apr 2019

BASE EARTHMAN bathroom wood frame

28 Apr 2019

BASE EARTHMAN first ceiling beams set up

28 Apr 2019

BASE EARTHMAN beam positioning

28 Apr 2019

BASE EARTHMAN recycled rafters as door lintel

21 Mar 2019

BASE EARTHMAN morning light on site

20 Mar 2019

BASE EARTHMAN wooden structure for bathroom

20 Mar 2019

BASE EARTHMAN separation wall building

20 Mar 2019

BASE EARTHMAN separation wall base preparation

20 Mar 2019

BASE EARTHMAN plumbing setting up in bathroom

20 Mar 2019

BASE EARTHMAN separation wall frame

20 Mar 2019

BASE EARTHMAN wooden wall construction

20 Mar 2019

BASE EARTHMAN preparation for plumbing

6 Mar 2019

BASE EARTHMAN interior actions

6 Mar 2019

BASE EARTHMAN interior construction continues

16 Feb 2019

BASE EARTHMAN -- wintersleep --

16 Feb 2019

BASE EARTHMAN_Placing insulation on ground-façade encounter & waterproofing membrane

4 Dec 2018

BASE EARTHMAN_Placing insulation on ground-façade encounter

28 Nov 2018

BASE EARTHMAN_Fixing wind-tight paper

26 Nov 2018

BASE EARTHMAN_Removing scaffolding

21 Nov 2018

BASE EARTHMAN_Placing jute insulation

20 Nov 2018

BASE EARTHMAN_Window placement

16 Nov 2018

BASE EARTHMAN_Removing wallpaper & creating slanted window opening

15 Nov 2018

BASE EARTMAN_Window installation

14 Nov 2018

BASE EARTMAN_Repairing existing wooden beams

13 Nov 2018

BASE EARTMAN_Woodworkers placing windows & removal of wallpaper

12 Nov 2018

BASE EARTHMAN_Woodworkers working on the facades

9 Nov 2018

BASE EARTHMAN_Finishing the separation wall

8 Nov 2018

BASE EARTHMAN_Working on separation wall & setting up the structure for the facade

7 Nov 2018

BASE EARTHMAN_Preparing the site for woodworkers

6 Nov 2018

BASE EARTHMAN_Finishing demolition part & saying goodbye to the last container

5 Nov 2018

BASE EARTHMAN_Starting new separation wall

1 Nov 2018

BASE EARTHMAN_Removal of wooden beam & earth movements

30 Oct 2018

BASE EARTHMAN_Cutting the roof

25 Oct 2018

BASE EARTHMAN_Preparing roof for cutting

23 Oct 2018

BASE EARTHMAN_Demolition of the last wall & removal of toilet tiles

22 Oct 2018

BASE EARTHMAN_Sifting local earth for the new oven & insulating the terrace

20 Oct 2018

BASE EARTHMAN_ Receiving & organazing the thermal insulation

19 Oct 2018

BASE EARTHMAN_Visiting the carpentry

18 Oct 2018

BASE EARTHMAN_Preparation of space for new earth wall & removal of old floor tiles

16 Oct 2018

BASE EARTHMAN_ Construction of new lintel & organization of wooden beams

15 Oct 2018

BASE EARTHMAN_Creation of new concrete stair

11 Oct 2018

BASE EARTHMAN_Creation of new concrete slab

8 Oct 2018

BASE EARTHMAN_Preparation of formwork for concrete slab

3 Oct 2018

BASE EARTHMAN_Creation of new opening & preparation of formwork for concrete slab

2 Oct 2018

BASE EARTHMAN_Creation of new opening

1 Oct 2018

BASE EARTHMAN_Removing rammed earth wall formwork part 2

28 Sep 2018

BASE EARTHMAN_Finishing rammed earth wall

28 Sep 2018

BASE EARTHMAN_Removing upper floor & demolition of old walls and lintels

26 Sep 2018

BASE EARTHMAN_Removing rammed earth wall formwork part 1

20 Sep 2018

BASE EARTHMAN_Building rammed earth wall & upper floor lintel

20 Sep 2018

BASE EARTHMAN_Building rammed earth wall, installation of air pipes & opening of upper floor window

19 Sep 2018

BASE EARTHMAN_Building formwork for rammed earth wall & installation of wall heating

18 Sep 2018

BASE EARTHMAN_Removing upper floor windows, preparing concrete wall & removing floor

17 Sep 2018

BASE EARTHMAN_Demolition of old facade & arrival of earth sacks

15 Sep 2018

BASE EARTHMAN_Building masonry wall with earth mortar

14 Sep 2018

BASE EARTHMAN_Building slab extension

13 Sep 2018

BASE EARTHMAN_Building new facade & removing old windows

12 Sep 2018

BASE EARTHMAN_Building new facade & dismanteling kitchen

11 Sep 2018

BASE EARTHMAN_Building reinforced concrete beam, removing water pipes & dismanteling kitchen

10 Sep 2018

BASE EARTHMAN_Outdoor slab extension

7 Sep 2018

BASE EARTHMAN_Construction of entrance walls, demolition on upper floor & drainage of retaining wall

6 Sep 2018

BASE EARTHMAN_Framework for outer wall, construction of new walls & demolition of old entrance

4 Sep 2018

BASE EARTHMAN_Construction of conecting earth wall, interior opening & new plumbing installation

31 Aug 2018

BASE EARTHMAN_Finalising interior earth wall & creating interior openings

30 Aug 2018

BASE EARTHMAN_Construction of interior earth wall & preparation of drainage system

28 Aug 2018

BASE EARTHMAN_Construction of interior earth wall

24 Aug 2018

BASE EARTHMAN_Construction of interior earth wall, opening on concrete wall & removal of water pipes

22 Aug 2018

BASE EARTHMAN_Preparing wall frame, removal of windows, interior demolition & waterproofing of exterior retaining wall

21 Aug 2018

BASE EARTHMAN_Demolishing interior walls and floors & creating new openings

20 Aug 2018

BASE EARTHMAN_Removing screed, upper layer and pipes from flooring

26 Jul 2018

BASE EARTHMAN_Dismanteling master bathroom structure & demolishing internal walls

25 Jul 2018

BASE EARTHMAN_Demolishing living room floor, dismanteling furniture & Removing carpet and toilet finishing

24 Jul 2018

BASE EARTHMAN_Clearing out second floor, removing facade & visit from structural engineer

23 Jul 2018

BASE EARTHMAN_Demolishing balcony & dismanteling master bathroom

20 Jul 2018

BASE EARTHMAN_Removing balcony tiles & exterior ceiling

19 Jul 2018

BASE EARTHMAN_Removing 70s decoration and plumbing fixtures & outdoor ground filling

18 Jul 2018

BASE EARTHMAN_Demolition of internal walls, dismanteling sanitaries, taking out balcony railing & land stakeout

17 Jul 2018

BASE EARTHMAN_Removing roof beams & outdoor drainage

16 Jul 2018

BASE EARTHMAN_Removing top floor ceiling

13 Jul 2018

BASE EARTHMAN_Removing the wooden ceiling & demolising of internal walls

12 Jul 2018

BASE EARTHMAN_Taking out the glasswool insulation & wood structure on the roof

11 Jul 2018

BASE EARTHMAN_Demolition of concrete base & removal of the insulation of the roof

10 Jul 2018

BASE EARTHMAN_Setting up the workshop & preparing the site

9 Jul 2018

ramming at 77m height

10 Jan 2017

rendering fresh rammed earth wall surface 02

10 Jan 2017

rendering fresh rammed earth wall surface 01

10 Jan 2017

round wall in penthouse paraguay process 04

10 Jan 2017

round wall in penthouse paraguay process 03

10 Jan 2017

round wall in penthouse paraguay process 02

10 Jan 2017

round wall in penthouse paraguay process 01

10 Jan 2017

cielo raso - false ceiling gypsum board

3 Jun 2016

cielo raso - false ceiling cooling system

3 Jun 2016

120 days after the roof was supposed to be sealed there is still water coming in, and the ingeneers do not really have an idea why.

29 Apr 2016

earth rendering II

26 Apr 2016

earth rendering I

26 Apr 2016

reparation of broken cooling pipes running in the floor

25 Apr 2016

50% compaction of rammed earth floor

3 Apr 2016

adobe construction in cusco valley (peru)

25 Feb 2016

stone finishing of the tadelakt

17 Feb 2016

swiss Tadelakt-master Thomas Kuenzi

14 Feb 2016

the curved walls of the shower in the earth sauna will be rendered in the old tradition of TADELAKT

10 Feb 2016

the earthen carpet after the compaction

7 Feb 2016

the earth carpet is rolled out on the concrete slab

7 Feb 2016

earth mixture for rammed earth floor

4 Feb 2016

rammed earth floor on 60m height.

4 Feb 2016

Earth laboratory Asuncion

2 Feb 2016